JR line3 min read

Kashii Line

香椎線

The Kashii Line (香椎線, Kashii-sen) is a 25.4-kilometre railway line in Fukuoka Prefecture operated by the Kyushu Railway Company (JR Kyushu). It runs from Saitōzaki Station in Higashi-ku, Fukuoka, through the junction at Kashii, to Umi Station in the town of Umi in Kasuya District.

The line is laid to 1,067 mm narrow gauge, is single-track throughout, and is not electrified, yet since 2019 it has been worked entirely by BEC819 "DENCHA" battery-electric multiple units, which recharge from an overhead wire installed only inside the yard at Kashii. Carrying the line symbol JD and a blue line colour, it is also a line on which JR Kyushu has introduced automatic train operation.

FukuokaHigashiUmiSueHakataChuoShime5 km
Route of the Kashii Line · Fukuoka · Boundaries: MLIT / GSI / Japan Post

History

The railway began not as a passenger line but as a colliery carrier. It was built by the Hakata Bay Railway (博多湾鉄道), which opened the section between Saitōzaki and Sue on 1 January 1904, establishing stations including Saitōzaki, Nata, Doi, Chōjabaru (renamed Iga in 1908) and Sue. The purpose was to move coal from the Kasuya coalfield — in particular from a naval colliery at Shinbaru — out to the port at Saitōzaki. In June 1904 a temporary line was pushed on from Sue to Shinbaru so that the coal, which had until then been carted by road to Zassonokuma (today's Minami-Fukuoka), could be hauled directly by rail.

The line was then completed in stages. The Sue–Shinbaru section opened formally on 1 June 1905, and full-scale shipment of warship coal from the naval Shinbaru colliery began. On 29 December 1905 the extension from Shinbaru to Umi opened, completing the through line and establishing Umi Station. A goods branch, later known as the Tabiishi branch, followed: it opened from Sakado to Shime in 1909 and was extended from Shime to Tabiishi in 1915, serving the collieries of the district.

On 25 March 1920 the company, having taken up a shipping business, changed its name from Hakata Bay Railway to Hakata Bay Railway Steamship (博多湾鉄道汽船). Under the Land Transport Business Adjustment Act (陸上交通事業調整法), Hakata Bay Railway Steamship was absorbed into the Nishi-Nippon Railroad (Nishitetsu) on 19 September 1942, and the route became that company's Kasuya Line together with the Tabiishi freight branch.

The line passed to the state during the Second World War. On 1 May 1944 it was bought up and nationalised, so that the Nishi-Nippon Railroad Kasuya Line became the Japanese Government Railways' Kashii Line, together with the Kashii Line freight branch (the Tabiishi branch); at the same time Nata Station was renamed Gannosu. Freight, once the line's main purpose, was wound down over the following decades: the Shime–Tabiishi section of the Tabiishi branch was abolished in 1960, freight between Sakado and Umi ceased in 1981, and the remaining goods services and the rest of the branch were discontinued by 1985.

With the division and privatisation of Japanese National Railways, the Kashii Line passed to the Kyushu Railway Company (JR Kyushu) on 1 April 1987. JR Kyushu modernised operations steadily: line-wide one-man (driver-only) operation began in 1988, and in 1989 the nickname "Umi-no-Nakamichi Line" was announced for the Saitōzaki–Kashii section, which passes through Umi-no-Nakamichi. In 2015, twelve stations other than Chōjabaru and Kashii were converted to unstaffed "Smart Support Station" operation, and in 2017 centralised traffic control (CTC) and automatic route control (PRC) were brought into service across the whole line. A blue line colour and JD station numbering were adopted in 2018.

On 16 March 2019 the BEC819 "DENCHA" battery-electric multiple unit entered service on the Kashii Line, allowing electric-train operation on a route that has no continuous overhead wire — the trains charge from the electrified yard at Kashii. The non-electrified line then became a testbed for automatic driving: running trials of automatic train operation with the BEC819 were carried out on the Saitōzaki–Kashii section over the winter of 2019–2020, demonstration running in revenue service began in December 2020, and from 16 March 2024 some services began running under automatic operation with an attendant on board rather than a fully qualified driver.

Stations on this line

Timeline

  • 19041 January: the Hakata Bay Railway opens the Saitōzaki–Sue section, the line's first segment, to carry coal from the Kasuya coalfield to the port at Saitōzaki.
  • 19051 June: the Sue–Shinbaru section opens formally and full-scale shipment of warship coal from the naval Shinbaru colliery begins.
  • 190529 December: the Shinbaru–Umi extension opens, completing the through line and establishing Umi Station.
  • 19091 August: a freight branch from Sakado to Shime — the later Tabiishi branch — opens, serving the collieries of the district.
  • 192025 March: on taking up a shipping business, the company is renamed from Hakata Bay Railway to Hakata Bay Railway Steamship.
  • 194219 September: Hakata Bay Railway Steamship is absorbed into the Nishi-Nippon Railroad (Nishitetsu); the route becomes its Kasuya Line and the Tabiishi freight branch.
  • 19441 May: the line is bought up and nationalised — the Nishi-Nippon Railroad Kasuya Line becomes the Japanese Government Railways' Kashii Line (with the Tabiishi freight branch); Nata Station is renamed Gannosu.
  • 19851 January: the Sakado–Shime freight branch (the remainder of the Tabiishi branch, whose Shime–Tabiishi section had been abolished in 1960) and the Kashii–Sakado goods service are discontinued, ending the line's freight traffic (Sakado–Umi freight had ceased in 1981).
  • 19871 April: with the division and privatisation of Japanese National Railways, the Kashii Line passes to the Kyushu Railway Company (JR Kyushu).
  • 198813 March: line-wide one-man (driver-only) operation begins.
  • 198915 March: the nickname 'Umi-no-Nakamichi Line' is announced for the Saitōzaki–Kashii section, which passes through Umi-no-Nakamichi.
  • 201514 March: twelve stations other than Chōjabaru and Kashii are converted to unstaffed 'Smart Support Station' operation.
  • 201729 January: centralised traffic control (CTC) and automatic route control (PRC) enter service across the whole line.
  • 201916 March: the BEC819 'DENCHA' battery-electric multiple unit enters service, electrifying operation on a line with no continuous overhead wire; the trains charge from the yard at Kashii. (A blue line colour and JD station numbering had been adopted on 28 September 2018.)
  • 202024 December: demonstration running of automatic train operation begins in revenue service, following running trials with the BEC819 over the winter of 2019–2020.
  • 202416 March: some services begin running under automatic operation with an attendant on board rather than a fully qualified driver.

Sources